Change and

Project Management

                                                                            

Home Approach   Project Management Knowledge Case Studies Contact Us

                                         

 

Where am I? - Project Management Knowledge  ◊ Project Planning Overview

Project Planning Overview

The quotation and ultimately the business case are based around what the end-customer requires and how the organisation proposes to deliver those requirements. These can be further separated into confirmed and assumed. However for any that are assumed there is a risk that the assumption may not be correct which could adversely impact achievement of the project objectives. In most cases an organisation will therefore attempt to minimise the number of assumptions as soon as possible.

The different information categories are shown in the diagram below: J

The “What” (also called the Project Product) which needs to be delivered to the end customer typically includes elements of physical parts and submission documents. At project launch the majority of these will be confirmed, however some may still be assumed. Where any are assumed the worst case scenario they are not correct should be identified and managed through the standard risk management process.

 

The next step is for the team to identify all the deliverables, or elements of “How”, that will be needed to deliver the “What”. A sample of these is shown below. These are only the deliverables, not the activities that are required to produce them. These were created in Visio but they could be produced as a table in Excel etc.

 

The next step is to identify the dependencies between the deliverables. At this stage there is no consideration of resource constraints or specific timing, just the order of the deliverables. The example below only includes a sample of the deliverables from above:

The next step is to identify the activities and resource types / usage to produce each of the deliverables. If the organisation already has pre-defined Work Packages for the main deliverables this information will be largely generic and will just require a limited amount of project-specific customisation. Note: The use of Work Packages also limits the amount of activity detail that is needed in the timing plan.

 

Once the dependencies between all of the deliverables are understood, along with the activities / responsibilities for each one, it is possible to build them into a timing plan. The first pass does not take into account any resource constraints. An example is shown below: 

 

The basic plan can then be altered in order to level the required resources around the actual availability. The project stages can also be defined at this point. The example below shows levelled resource for illustration however the activities in the diagram have not actually been moved.

 

For more information, please contact us info@appliedlogic.ltd.uk or +44 (0) 7860 902530

 

©2016 Applied Logic Limited. All Rights Reserved

Our Business Policy